The latest update on the Construction of Metro Manila Subway started at Ugong, Valenzuela The line will have an underground depot in Ugong, Valenzuela, within the vicinity of the East Valenzuela station. It occupies 4 hectares (9.9 acres) of space and serves as the headquarters for the operations and maintenance of the line. The trains are parked on several sets of tracks, which converge onto the spur route and later on to the main network. The Project Total Cost is Php 356.96 billion pesos. Construction for the Ortigas and Shaw stations began on October 3, 2022, with the groundbreaking ceremony led by President Bongbong Marcos and Transportation Secretary Jaime Bautista. Work on the Katipunan and Anonas stations began on February 13, 2023. As of 31 January 2023, Phase 1 of the project is 37.48% complete. The Metro Manila Subway Project includes the construction of the 34-km railway line, Metro Manila Subway Project (MMSP) Phase I / Line 9, ROW Acquisition and Re...